21-moorfields-500-000-ft-fit-out-for-deutsche-bank-1
Deutsche Bank, 2025 City of London Building of the Year

21 Moorfields, London

Project procurement and scope

  • 2-Stage Design & Build.  c.500,000 ft2 over two buildings.
  • Shell & Core to CAT B fit out including all associated infrastructure.
  • Auditorium and event spaces, client floors, office floors, catering floor and inter-connecting staircases

Project role and responsibilities

  • Senior Planner (ISG Fit Out)
  • Developed programme from PQQ stage
  • Full responsibilty for all aspects of planning including a small team.

Key constraints/challenges to overcome

  • Ongoing basebuild delays and fixed Client migration dates meant considerable re-sequencing was required to maintain programme. This work took place over several months as areas were progressively handed over by the basebuild contractor.
brock-street-london-130-000-ft-cat-b-fit-out-for-facebook
Facebook

Brock Street, London

 

Project procurement and scope

  • Single Stage Design & Build.  c.130,000 ft2 over four floors
  • CAT B fit out including replacement plant, supporting infrastructure,
     lift refubishments and internal atrium staircase

Project role and responsibilities

  •  Planner (ISG Fit Out)
  •  Developed programme from Tender to Construction.
  •  Responsible for all aspects of planning and associated project controls.

Key constraints/challenges to overcome

  • Project delivered during Covid-19
  • Lift Contractor encountered several delays during fabrication, resulting in the programme being re-worked several times to accommodate.
netflix-london-8-floors-cat-a-to-cat-b-fit-out

Netflix, London

Project procurement and scope

  •  Single Stage Design & Build
  •  8 floors of CAT A to CAT B fit out including; Client floors, Office floors
     and three internal staircases.

Project role and responsibilities

  • Planner (ISG Fit Out)
  • Developed programme from Tender to Construction.
  • Responsible for all aspects of planning and associated project
     controls

Key constraints/challenges to overcome

  • Project delivered during Covid-19
  • Managed several re-sequencing exercises in line with discoverables, Client design changes and MEP phasing.